Promotional feature: Alliance Leisure - Design & Build part 10

The design and build stages of a project can be, potentially, the most bumpy. Alliance Leisure business development managers James Foley and Julia Goddard share how they helped smooth the way for clients in Doncaster and Cwmbran

Published in Health Club Management 2015 issue 6
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym

How is the process managed?
From the start, Alliance works to develop the scheme concepts affordably and innovatively with the client and our property consultants Savernake Property, and other contractors. This is very different to other approaches where design and build outcomes can’t be delivered because only one contractor was involved at the start.

How does the design and build process begin?
Alliance has a unique approach and works with clients from the start and at every step until the project is delivered successfully. As Business Development Manager this involves establishing the project is viable before thinking about how that concept might look. We’ll look to increase participation by adapting, reinvigorating or in cases such as Adwick Leisure Centre in Doncaster, totally transforming an underutilised space to create something different but relevant to users.

What was the brief a Adwick? Doncaster Culture and Leisure Trust (DCLT) wanted to explore options for increasing fitness provision at the site and improving the overall centre offering – looking at the facility catchment and competition – such as the introduction of new academy sports hall facilities. Our design team created a journey through the site with three distinct areas which all feel like they belong. Where the sports hall used to be, there is a new ‘family adventure’ area at ground level, with ten pin bowling, café, bar and play facilities. Upstairs there is a newly formed mezzanine ‘fitness’ area, with a space for large scale fitness fitted out by DCLT, along with studio provision and changing rooms, and the modernised reception leads through to the pool.

What about changes at the design and build stages?
Alliance works with the client to create a vision and design the project. As the build commences the vision on paper or a 3D model can look different to the real thing. We can adapt the design and change the build while ensuring that the total project cost is still maintained.

How are challenges along the way overcome?
No build project ever runs perfectly smoothly, but commissioning surveys and expertise at the start helps us avoid risks where possible. With issues that would normally fall outside of our remit, we work with the client to see how we could cost effectively integrate these into the project. For instance at Adwick Leisure Centre, putting in new ten pin bowling, 100 stations of gym equipment and new infrastructure will add power requirements to the site. Instead of paying for an expensive new supply, we gave Doncaster Leisure Trust the option to work creatively with our team to use energy saving techniques, avoiding unnecessary cost and keeping energy performance within existing limits.

What marks the end of the design and build process?
The end of the process for Alliance doesn’t stop when the build is complete. We then ensure a robust handover takes place and work with partners to train staff to operate elements, such as the bowling at Adwick. We work hard to resolve late snags, and are proud that our repeat project rate with clients is high – a testament to us having clients’ interests as our number one priority.

Follow the series

To view the whole series of articles on Alliance Leisure’s offering, visit: www.healthclubmanagement.co.uk/allianceleisure

1. Scoping/investigation
2. Conceptualisation
3. Viability assessment
4. Site investigation
5. Fixed price contracts
6. Overseeing the building work
7. Ordering phase
8. Client support (part 1)
9. Client support (part 2)
10. Design & Build

CASE STUDY

Cwmbran Stadium, Torfaen Leisure Trust

Alliance Leisure recently redesigned and converted Cwmbran Stadium’s four­-court sports hall into its newly branded ‘Go Vertical’ activity zone, including an 18 element VerTgo climbing area, large soft play and cafe. The main reception and atrium were also modernised and the old café was converted to a 75­-station fitness suite. The outdoor grass pitch is also being converted to a 3G surface. Sally Church, chief executive officer of Torfaen Leisure Trust (TLT) says: “The project was designed with us to suit our requirements. We wanted a project that would generate income and increase participation, and would also look very different, not municipal.”

Alliance Leisure worked with operators Torfaen Leisure Trust and the design team consisting of Createability for construction and Bicknell Shacklady Ewing for interior design. During designing, the design team had to solve the problem of a low ceiling in the former cafe area, which was to be converted into a fitness suite. “Instead of making major structural changes, we designed and created the suite around the ceiling height and planned the space accordingly,” says Julia Goddard, business development manager for Alliance Leisure. “It now has 75 stations with wide windows facing out on to the track, giving lots of natural light.”

Goddard adds: “During the build, issues with the location of the Go Vertical climbing briefing area were found, so rather than spend additional money to sort this out we took a week as a team to solve the problem and ended up locating the briefing area into the main activity space, which has worked really positively and saved costs of around £20,000.”

“Every issue or problem we have come across has been resolved,” adds Church. “The whole process has worked because we all took a ‘solutions not problems approach.’ Now we are working with Alliance on sales and marketing for both the gym and the Go Vertical climbing area.”

Cwmbran Stadium’s old sports hall has been converted into an 18-element VerTgo climbing centre
Cwmbran Stadium’s old sports hall has been converted into an 18-element VerTgo climbing centre
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space

Find out more:

www.allianceleisure.co.uk
Tel: +44 (0)1278 444944

Sign up here to get HCM's weekly ezine and every issue of HCM magazine free on digital.
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
https://www.leisureopportunities.co.uk/images/960919_688681.jpg
Alliance Leisure smoothed the way through design and build for clients in Doncaster and Cwmbran
business development managers James Foley and Julia Goddard,Alliance leisure, design, build
HCM magazine
HCM People

Stephen Price

Founder, SP&Co Group
Working in public health over the last few years has lit up parts of my brain again
HCM magazine
I experienced a blissful feeling of joy I hadn’t felt since I was a kid
HCM magazine
Strength training is evolving, driven by changing consumer preferences. Julie Cramer talks to innovators about how their products are meeting this demand
HCM magazine
Raphael Cuomo explores the powerful link between addiction, health and behaviour change
HCM magazine
Small improvements to sleep, diet and physical activity have major benefits for the heart, according to new research from the University of Sydney
HCM promotional features
Sponsored
Third Space partnered with IndigoFitness to deliver a bespoke training space for its new club at The Whiteley
HCM promotional features
Sponsored
Greg Bradley looks at the shift towards strength training in gyms and advises on how operators can create the ultimate training environment
HCM promotional features
Sponsored
SnowDome Fitness has added 50 per cent more space with cutting-edge Technogym solutions
HCM promotional features
Sponsored
Starpool supports Olympic champion Marcell Jacobs, says Riccardo Turri
HCM promotional features
Sponsored
Find out how your gym can tap into the corporate wellness boom
HCM promotional features
Sponsored
David Lloyd is stepping up its commitment to women’s health as it continues to explore what fit-for-purpose looks like for the female population
HCM promotional features
Sponsored
EGYM has opened a new HQ in Paternoster Square, London and revealed a range of new launches
HCM promotional features
Promotion
Performance Health Systems, manufacturer of Power Plate, has a new CEO, with an ambitious vision for the company
HCM promotional features
Sponsored
Pulse Fitness has created a new health club delivering an elevated wellness experience
HCM promotional features
Latest News
Nuffield Health has told HCM that it takes its responsibilities towards its colleagues seriously and ...
Latest News
Technogym has announced the launch of the Run X World Treadmill Championship, the first world ...
Latest News
Shocked by the UK loneliness statistics, charitable trust Mytime Active has been doubling down on ...
Latest News
Portugal’s leading operator, SC Fitness, is celebrating a milestone by reaching 100 gyms.  The company ...
Latest News
Australia’s fast-growing fitness network, Viva Leisure, is adding a low-cost gym brand to its already ...
Latest News
Speedflex has launched a strength training programme for 10 to 16-year-olds, to make it safer, ...
Latest News
Tewinbury Farm Hotel in Hertfordshire, UK is expanding its premium leisure proposition with the launch ...
Latest News

Work is underway in Madrid on one of Europe’s most significant multi-functional complexes, ...

Opinion
promotion
Strength training has moved from the margins to the mainstream.
Opinion: Building smarter strength spaces for today’s operators
Featured supplier news
Featured supplier news: W3Fit EMEA celebrates its fifth anniversary
Celebrating its milestone 5th anniversary, W3Fit EMEA returns in 2026 with an unmissable gathering of the Health & Fitness industry’s most influential leaders.
Featured supplier news
Featured supplier news: Elevate 2026 to mark 10-year anniversary with biggest ever waterfront drinks reception
Elevate is set to celebrate its 10th anniversary in style this June, with organisers confirming the event’s largest-ever drinks reception as registrations continue to run more than 10% ahead of last year.
Company profiles
Company profile: FIBO
FIBO pursues the vision of a strong and healthy society and as a global network ...
Company profiles
Company profile: Myzone
Myzone is a global pioneer of Motivation Technology (MoTech), redefining fitness by turning behavioural science ...
Supplier Showcases
Supplier Showcase - From nightclub to health club
Supplier Showcases
Supplier Showcase - Future-proofing
Catalogue Gallery
Click on a catalogue to view it online
Featured press releases
GYMNATION press release: Massive ‘Good Luck’ message appears in Saudi Desert as Green Falcons head to World Cup
Passengers flying out of Riyadh this week have been treated to an extraordinary sight from the skies after GymNation unveiled a giant desert sand mural supporting the Saudi Arabia National Football Team ahead of the FIFA World Cup in the United States.
Featured press releases
BLK BOX press release: BLK BOX strengthens European growth with the appointment of Germany country manager Timo Garrels
BLK BOX is proud to welcome Timo Garrels as Germany country manager, marking another important step in the brand’s continued growth across Europe.
Directory
Spa and beauty equipment
Oakworks Inc: Spa and beauty equipment
Fitness tracking platform
SpiviTech: Fitness tracking platform
Hot tubs
MSpa International Ltd: Hot tubs
Lockers
Crown Sports Lockers: Lockers
Water experiences and hydrotherapy solutions
Aquaform s.r.l.: Water experiences and hydrotherapy solutions
Industrial washing machines
Miele Company Limited: Industrial washing machines
Property & Tenders
Stratford, East London.
Lee Valley Regional Park Authority
Property & Tenders
Y Felinheli, LL56 4QN
Newmark
Property & Tenders
Diary dates
13-13 Jun 2026
Worldwide, Various,
Diary dates
21-24 Sep 2026
The Langham Huntington Pasadena , Pasadena, United States
Diary dates
06-08 Oct 2026
Messe Stuttgart, Stuttgart, Germany
Diary dates
22-22 Oct 2026
QEII Conference Centre, London,
Diary dates
26-29 Oct 2027
Koelnmesse Exhibition Centre, Cologne, Germany
Diary dates

features

Promotional feature: Alliance Leisure - Design & Build part 10

The design and build stages of a project can be, potentially, the most bumpy. Alliance Leisure business development managers James Foley and Julia Goddard share how they helped smooth the way for clients in Doncaster and Cwmbran

Published in Health Club Management 2015 issue 6
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym

How is the process managed?
From the start, Alliance works to develop the scheme concepts affordably and innovatively with the client and our property consultants Savernake Property, and other contractors. This is very different to other approaches where design and build outcomes can’t be delivered because only one contractor was involved at the start.

How does the design and build process begin?
Alliance has a unique approach and works with clients from the start and at every step until the project is delivered successfully. As Business Development Manager this involves establishing the project is viable before thinking about how that concept might look. We’ll look to increase participation by adapting, reinvigorating or in cases such as Adwick Leisure Centre in Doncaster, totally transforming an underutilised space to create something different but relevant to users.

What was the brief a Adwick? Doncaster Culture and Leisure Trust (DCLT) wanted to explore options for increasing fitness provision at the site and improving the overall centre offering – looking at the facility catchment and competition – such as the introduction of new academy sports hall facilities. Our design team created a journey through the site with three distinct areas which all feel like they belong. Where the sports hall used to be, there is a new ‘family adventure’ area at ground level, with ten pin bowling, café, bar and play facilities. Upstairs there is a newly formed mezzanine ‘fitness’ area, with a space for large scale fitness fitted out by DCLT, along with studio provision and changing rooms, and the modernised reception leads through to the pool.

What about changes at the design and build stages?
Alliance works with the client to create a vision and design the project. As the build commences the vision on paper or a 3D model can look different to the real thing. We can adapt the design and change the build while ensuring that the total project cost is still maintained.

How are challenges along the way overcome?
No build project ever runs perfectly smoothly, but commissioning surveys and expertise at the start helps us avoid risks where possible. With issues that would normally fall outside of our remit, we work with the client to see how we could cost effectively integrate these into the project. For instance at Adwick Leisure Centre, putting in new ten pin bowling, 100 stations of gym equipment and new infrastructure will add power requirements to the site. Instead of paying for an expensive new supply, we gave Doncaster Leisure Trust the option to work creatively with our team to use energy saving techniques, avoiding unnecessary cost and keeping energy performance within existing limits.

What marks the end of the design and build process?
The end of the process for Alliance doesn’t stop when the build is complete. We then ensure a robust handover takes place and work with partners to train staff to operate elements, such as the bowling at Adwick. We work hard to resolve late snags, and are proud that our repeat project rate with clients is high – a testament to us having clients’ interests as our number one priority.

Follow the series

To view the whole series of articles on Alliance Leisure’s offering, visit: www.healthclubmanagement.co.uk/allianceleisure

1. Scoping/investigation
2. Conceptualisation
3. Viability assessment
4. Site investigation
5. Fixed price contracts
6. Overseeing the building work
7. Ordering phase
8. Client support (part 1)
9. Client support (part 2)
10. Design & Build

CASE STUDY

Cwmbran Stadium, Torfaen Leisure Trust

Alliance Leisure recently redesigned and converted Cwmbran Stadium’s four­-court sports hall into its newly branded ‘Go Vertical’ activity zone, including an 18 element VerTgo climbing area, large soft play and cafe. The main reception and atrium were also modernised and the old café was converted to a 75­-station fitness suite. The outdoor grass pitch is also being converted to a 3G surface. Sally Church, chief executive officer of Torfaen Leisure Trust (TLT) says: “The project was designed with us to suit our requirements. We wanted a project that would generate income and increase participation, and would also look very different, not municipal.”

Alliance Leisure worked with operators Torfaen Leisure Trust and the design team consisting of Createability for construction and Bicknell Shacklady Ewing for interior design. During designing, the design team had to solve the problem of a low ceiling in the former cafe area, which was to be converted into a fitness suite. “Instead of making major structural changes, we designed and created the suite around the ceiling height and planned the space accordingly,” says Julia Goddard, business development manager for Alliance Leisure. “It now has 75 stations with wide windows facing out on to the track, giving lots of natural light.”

Goddard adds: “During the build, issues with the location of the Go Vertical climbing briefing area were found, so rather than spend additional money to sort this out we took a week as a team to solve the problem and ended up locating the briefing area into the main activity space, which has worked really positively and saved costs of around £20,000.”

“Every issue or problem we have come across has been resolved,” adds Church. “The whole process has worked because we all took a ‘solutions not problems approach.’ Now we are working with Alliance on sales and marketing for both the gym and the Go Vertical climbing area.”

Cwmbran Stadium’s old sports hall has been converted into an 18-element VerTgo climbing centre
Cwmbran Stadium’s old sports hall has been converted into an 18-element VerTgo climbing centre
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space
The stadium’s former cafe area has been converted into a 75-station fitness suite, and the new design lets light flood into the space

Find out more:

www.allianceleisure.co.uk
Tel: +44 (0)1278 444944

Sign up here to get HCM's weekly ezine and every issue of HCM magazine free on digital.
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
The Alliance project at Adwick Leisure Centre in Doncaster included a new ten pin bowling area and a 100-station gym
https://www.leisureopportunities.co.uk/images/960919_688681.jpg
Alliance Leisure smoothed the way through design and build for clients in Doncaster and Cwmbran
business development managers James Foley and Julia Goddard,Alliance leisure, design, build
Latest News
Nuffield Health has told HCM that it takes its responsibilities towards its colleagues seriously and ...
Latest News
Technogym has announced the launch of the Run X World Treadmill Championship, the first world ...
Latest News
Shocked by the UK loneliness statistics, charitable trust Mytime Active has been doubling down on ...
Latest News
Portugal’s leading operator, SC Fitness, is celebrating a milestone by reaching 100 gyms.  The company ...
Latest News
Australia’s fast-growing fitness network, Viva Leisure, is adding a low-cost gym brand to its already ...
Latest News
Speedflex has launched a strength training programme for 10 to 16-year-olds, to make it safer, ...
Latest News
Tewinbury Farm Hotel in Hertfordshire, UK is expanding its premium leisure proposition with the launch ...
Latest News

Work is underway in Madrid on one of Europe’s most significant multi-functional complexes, ...

Latest News
PureGym is encouraging people to step away from their screens and go for a walk, ...
Latest News
Small improvements to sleep, diet quality, and physical activity, made in combination lead to a ...
Latest News
Therme Manchester’s 28-acre development, which will include interconnected glass pavilions that measure 65,000sq m, will ...
Opinion
promotion
Strength training has moved from the margins to the mainstream.
Opinion: Building smarter strength spaces for today’s operators
Featured supplier news
Featured supplier news: W3Fit EMEA celebrates its fifth anniversary
Celebrating its milestone 5th anniversary, W3Fit EMEA returns in 2026 with an unmissable gathering of the Health & Fitness industry’s most influential leaders.
Featured supplier news
Featured supplier news: Elevate 2026 to mark 10-year anniversary with biggest ever waterfront drinks reception
Elevate is set to celebrate its 10th anniversary in style this June, with organisers confirming the event’s largest-ever drinks reception as registrations continue to run more than 10% ahead of last year.
Company profiles
Company profile: FIBO
FIBO pursues the vision of a strong and healthy society and as a global network ...
Company profiles
Company profile: Myzone
Myzone is a global pioneer of Motivation Technology (MoTech), redefining fitness by turning behavioural science ...
Supplier Showcases
Supplier Showcase - From nightclub to health club
Supplier Showcases
Supplier Showcase - Future-proofing
Catalogue Gallery
Click on a catalogue to view it online
Featured press releases
GYMNATION press release: Massive ‘Good Luck’ message appears in Saudi Desert as Green Falcons head to World Cup
Passengers flying out of Riyadh this week have been treated to an extraordinary sight from the skies after GymNation unveiled a giant desert sand mural supporting the Saudi Arabia National Football Team ahead of the FIFA World Cup in the United States.
Featured press releases
BLK BOX press release: BLK BOX strengthens European growth with the appointment of Germany country manager Timo Garrels
BLK BOX is proud to welcome Timo Garrels as Germany country manager, marking another important step in the brand’s continued growth across Europe.
Directory
Spa and beauty equipment
Oakworks Inc: Spa and beauty equipment
Fitness tracking platform
SpiviTech: Fitness tracking platform
Hot tubs
MSpa International Ltd: Hot tubs
Lockers
Crown Sports Lockers: Lockers
Water experiences and hydrotherapy solutions
Aquaform s.r.l.: Water experiences and hydrotherapy solutions
Industrial washing machines
Miele Company Limited: Industrial washing machines
Property & Tenders
Stratford, East London.
Lee Valley Regional Park Authority
Property & Tenders
Y Felinheli, LL56 4QN
Newmark
Property & Tenders
Diary dates
13-13 Jun 2026
Worldwide, Various,
Diary dates
21-24 Sep 2026
The Langham Huntington Pasadena , Pasadena, United States
Diary dates
06-08 Oct 2026
Messe Stuttgart, Stuttgart, Germany
Diary dates
22-22 Oct 2026
QEII Conference Centre, London,
Diary dates
26-29 Oct 2027
Koelnmesse Exhibition Centre, Cologne, Germany
Diary dates
Search news, features & products:
Find a supplier:
We Work Well Events
We Work Well Events
Partner sites